I'm Chief Revenue Officer at a rail equipment manufacturer. Our CEO wants us to bid on a large transit maintenance RFP. Bids are due Friday, December 11, and I've promised him a go/no-go by Friday, December 4. Today is Tuesday, December 1. Below are his email, a summary of the RFP and its terms, our bid team's note, legal's comments, and our sales operations notes on the customer.
Please give me a one-page go/no-go:
1. My recommendation: bid, don't bid, or bid only if…, in two sentences.
2. Anything that rules us out or breaks our own policy, with the input that shows it.
3. What the deal is really worth, and what it could cost us, on the RFP's own terms.
4. What would change the answer, who decides each point, and by when.
Read the terms for what could disqualify us or cost us, not only for what we could win. Check every date against our own plan. Don't add facts that aren't in the inputs; if you assume something, say so.
[1] Email from Martin Hale, CEO
Ruth, this is the one we've been waiting for: $140M over 8 years with Northshore Transit. It's strategic and it gets us into North American transit. I want us to bid. Your call by Friday.
[2] RFP summary and key terms (Northshore Transit, bogie overhaul and spares)
- Scope: overhaul of 320 bogies over 8 years, plus spare parts. The first 40 overhauled by June 30, 2027.
- Mandatory at submission: IRIS rail quality certification (ISO/TS 22163) for the site doing the work.
- Liquidated damages: 1% of contract value for each week any milestone is late. No cap.
- At least 25% of contract value performed in the province.
- Price fixed for the full 8 years, with no escalation.
- Clarification questions close Friday, December 4.
[3] Note from the bid team
We'd do the work at our Hamilton site, which is in the province. Hamilton's IRIS certification audit is booked for February 2027. Our price gives a 14% margin at today's steel prices. At current capacity, Hamilton can deliver the first 40 bogies by September 2027.
[4] Comments from legal
Our policy caps liquidated damages at 10% of contract value; anything uncapped needs board approval. Our pricing policy allows fixed prices for up to 3 years without indexation.
[5] Sales operations notes on Northshore
The incumbent has supplied Northshore for 12 years. Northshore has run three similar RFPs since 2019, and the incumbent won all three. The $140M is Northshore's budget estimate; the RFP says the award may be split between up to two suppliers.